Beatrice Morrow Construction Updates: 7/11

July 11, 2017 · by pcriadmin · PCRI, The Beatrice Morrow
Forms are placed for concrete first floor walls at the Beatrice Morrow building

Forms are placed for concrete first floor walls at the Beatrice Morrow building

We’re going up! Following completion of concrete footings,¬†first floor columns and walls¬†are being formed, reinforced, and concrete will be poured. This work will be completed in three phases with each phase lasting approximately one week.

During the coming weeks, some street closures are expected in order to ensure safety and facilitate this work:

  • Ivy Street at NE Martin Luther King Blvd: 7/7-7/13 and 7/17
  • Parking spaces on NE Cook Street near NE Martin Luther King Blvd until 11/13

Additional information and prior construction updates can be found HERE. Completion of the 80-unit mixed-use commercial and residential building is anticipated in mid-2018 and all apartments are expected to be leased by the end of 2018.