Beatrice Morrow Construction Updates: 6/6

June 7, 2017 · by pcriadmin · PCRI, The Beatrice Morrow
Excavation and site work begins at the Beatrice Morrow site

Excavation and site work begins at the Beatrice Morrow site

During the final week of May, construction activity progressed at The Beatrice Morrow Apartments. Work primarily consisted of installation of the storm water drainage systems and excavation for building footings. Installation of concrete forms and additional preparation for building footings will continue in early June.

For the week of June 12, construction crews will close NE Ivy Street where it meets Martin Luther King Jr. Blvd. to allow for installation of the sanitary sewer connection. The street will be closed beginning Monday or Tuesday and may last through the week. Crews will re-open the road as soon as it is safe to do so. East of the work site, Ivy Street will remain open to NE 7th Avenue. Additional intermittent closures are likely to occur in the coming weeks to ensure safety while concrete pours are performed. Details of future street closures will be communicated as soon as they are confirmed.

The City of Portland is reviewing the development team’s proposed Transportation Management Plan which details any additional construction-related impacts sidewalks and streets. Once approved by the Portland Bureau of Transportation, this information will be shared by the development team.

Additional information and prior construction updates can be found HERE. Completion of the 80-unit mixed-use commercial and residential building is anticipated in mid-2018 and all apartments are expected to be leased by the end of 2018.